Case Study

DATE

June 28, 2020

LOCATION

Abbey Wood

DIVISONS

Bridge Demolition - Abbey Wood

Services

Bridge demolition; waste and environmental management; site mobilisation and demobilisation; protection of working culvert; road traffic management.

Project duration

Bank holiday weekend

Summary

Econ was commissioned to demolish and clear a concrete footbridge spanning a four lane highway. Timing was critical to ensure that disruption to traffic and local residents was kept to a minimum. Working ‘round the clock’ over a four day weekend period the Econ team successfully demolished and disposed of a large concrete structure in a controlled, efficient and safe operation. A carefully planned convoy approach ensured that all waste material was removed and recycled in the most environmentally friendly way possible.

Staffing requirements

Careful and detailed planning was essential and the works were overseen and coordinated by one of our highly experienced project managers. Key staff included demolition technicians, and a team of waste removal and recycling operatives. By using our own material recycling facilities and pre-selected and vetted sites we were able to clear a large quantity of waste arising from the demolition over the four day period.

Equipment/Plant Used

1 x 35t 360 Excavator with a Concrete Cruncher attachment, 3 x 23t 360 Excavators with Breaker and Grab attachments, 1 x 15t 360 Excavator with Selecta Grab attachment and 1 x 360 Telehandler.

Similar Case Studies

“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”

Demolition and Asbestos Removal Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.