Case Study

DATE

July 7, 2020

LOCATION

Dartford

DIVISONS

Conway House

Services

Demolition

Project duration

Three Weeks

Summary

Econ Construction were commissioned to carry out the demolition of FM Conway’s former office in Dartford, Kent.

The structure to be demolished was steel frame construction with brick infill and concrete hollow pot roof.  The demolition was undertaken with great care and attention as the structure was connected to adjoining structures that had to remain operational.

This was achieved using diamond sawing and hand demolition to separate the structures before completing the demolition using mechanical demolition excavators.

The project was completed to budget and programme with no reportable incidents throughout the works.

Staffing requirements

ARCA Trained Asbestos Managers through to Operatives, Econ’s team included staff who met the following requirements: Emergency First Aid, IPAF, CPCS, CSCS

Equipment/Plant Used

1 X 20 tonne excavator, skip lorry, hand tools and diamond drilling equipment.

Similar Case Studies

In short, the service received by yourselves has been faultless in terms of works carried out for London Bridge DU. The response times in emails as well as getting to site to do the works is very efficient, and should there be any issues, the communication from all at Econ who I’ve dealt with has been professional. Thank you,

Waste & Fly Tipping Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.