Harrow Manorway

Download PDF
Download PDFDownload PDF

DATE

July 7, 2020

LOCATION

Thamesmead, South East London

DIVISONS

Project Summary

Services

Footbridge Demolition

Project duration

1 Weekend Road Closure from 21:00hrs Friday to Monday morning at 03:00hrs

Summary

Econ were contracted by FM Conway to carry out the design and demolition of Harrow Manorway footbridge in Thamesmead, South East London.

Works were carried out during a full highway closure from 21:00hrs on a Friday Night through until Monday morning at 05:00hrs.

Works were all completed ahead of schedule at 14:00hrs on the Sunday Afternoon.

Staffing requirements

Full time Project Manager, Quantity Surveyor, Site Manager. Econ’s team included staff who met the following requirements: SSTS, CCDO and CPCS Plant Operators

Equipment/Plant Used

1 x Demolition Spec 35t Excavator, 2 x 25t Demolition Spec Excavators, 1 x 15t Demolition Excavators & 1 x Telehandler

Similar Case Studies

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.