Footbridge Demolition
1 Weekend Road Closure from 21:00hrs Friday to Monday morning at 03:00hrs
Econ were contracted by FM Conway to carry out the design and demolition of Harrow Manorway footbridge in Thamesmead, South East London.
Works were carried out during a full highway closure from 21:00hrs on a Friday Night through until Monday morning at 05:00hrs.
Works were all completed ahead of schedule at 14:00hrs on the Sunday Afternoon.
Full time Project Manager, Quantity Surveyor, Site Manager. Econ’s team included staff who met the following requirements: SSTS, CCDO and CPCS Plant Operators
1 x Demolition Spec 35t Excavator, 2 x 25t Demolition Spec Excavators, 1 x 15t Demolition Excavators & 1 x Telehandler