Case Study

DATE

July 7, 2020

LOCATION

Feltham

DIVISONS

Feltham Cycle Footbridge

Services

Dismantling of existing cycle footbridge

Project duration

1 x 12 hour possession

Summary

Econ was contracted on behalf of Network Rail for the dismantling of the ramp section and main span of the existing cycle footbridge in close proximity to Feltham railway station.

The works consisted of careful planning to ensure it was carried out during a 12 hour possession of the track, using a Kirow rail mounted crane to assist dismantling of the footbridge, which was over 30 meters in length and weighing 25 tonnes. The main span was lifted into a laydown area and was then cut into 10 meter sections, using oxy propane cutting equipment so it could be transported to another location using articulated flatbed vehicles. The sections were then lifted off the transport using a 60 tonne mobile crane and stored in the Network Rail yard.

Staffing requirements

2 x Demolition managers, 2 x Demolition managers, 2 x hot cutting operatives, 6 x demolition operatives. Econ’s team included staff who met the following requirements: CCDO certification, PTS certification, Safety in gas cutting and CPCS D90 certification (demolition plant).

Equipment/Plant Used

1 x rail mounted kirow crane, 1 x 60 tonne mobile crane, 4 x articulated flatbed vehicles, 1 x roll on off vehicle and 1 x 20 tonne demolition excavator.

Similar Case Studies

“We were impressed with the approach used by you operation team to carry out the works both professional and diligently. Econ were very accommodating to meet our needs from the initial presentations prepared on strategy to mitigate risks and throughout execution of the works and keeping us fully informed and giving us the confidence we needed. The approach of Econ Site supervisors and visiting managers through to operatives on site was always of a high standard and good-natured and we are pleased to give credit where it is due. On site initiatives by the team from demonstrations /videos of emergency procedures when working in asbestos enclosures and working with consistent site uniforms contributed to the site achieving a Kier ‘Blue’ for best practice and working above standards. This was an excellent example of collaborative working and a joint approach to promptly overcome some of the challenges with asbestos and how best to deal with this along with working near challenging neighbours’ properties, the school and the church.”

Demolition and Asbestos Removal Sept 2023

Our Accreditations

Enabling
Teamwork
Enabling
Health & Safety
Enabling
Excellence
Enabling
Growth

Subscribe to our Newsletter!

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.