Case Study

Redundant Electrical Sub Station

Services

Decommissioning of Redundant Electrical Sub-Station

Project duration

4 Weeks

Summary

Econ were contracted to remove asbestos and demolish a redundant UKPN sub-station. The site covered over 4000 m2

Works involved removing all the asbestos from the switchgear, removing and disposing of the redundant plant, cable and concrete structures.

Works were completed within the required programme with no accidents or incidents.

Staffing requirements

Staff undertook site specific inductions and all staff were Asbestos and Demolition trained. All machine operators held CPCS qualifications.. Econ’s team included staff who met the following requirements: CCDO, CCDO Burning Operatives and IPAF Operatives

Equipment/Plant Used

25t 360 Excavator, Articulated Booms, Oxy/Propane Cutting Equipment, Recipriocating Saws, Low Loaders, Skip Lorries, Ekki Mats for Protection of remaining assets and telehandler.

Econ brochure.

Download our FREE brochure

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.